Markham Building Permit for a Commercial Unit: Steps and Papers

A Markham building permit for a commercial unit is filed online in ePLAN with a Declaration of Use and designer forms. Steps, review times, contacts.

Markham Building Permit for a Commercial Unit: Steps and Papers, commercial construction work by Ardenvale Construction in Ontario

A Markham building permit for a commercial unit is applied for online in the City's ePLAN system, with a Declaration of Use, scaled drawings from a qualified designer and a zoning check before you start. Paper applications are no longer accepted, and work can only begin once the permit is issued.

This guide is for tenants, owners and property managers planning a build-out in Markham. We read the City's own permit process, guide, forms, licensing and development charge pages and put them in the order a project follows. If you want a contractor who plans this stage first, see our tenant improvements work, and our service areas page shows where we build.

Markham publishes its review targets in business days, so a schedule can be planned around the City's own numbers, shown below.

Which Markham building permit does my commercial project need?

Markham splits non-residential work into three permit types, and the first decision is which one you hold. An Alterations permit covers an interior alteration on any building except housing, while a Non-Housing permit covers new buildings, additions, exterior alterations and any interior work that changes the use. Plumbing-only work needs its own plumbing permit.

Which Markham permit matches which commercial project. Source: City of Markham Guide to Building Permits, read November 19, 2026.
Your projectPermit typeWhat the City adds
Tenant fit-up, same useAlterations (AL)New partitions, interior demolition, mechanical or fire protection changes
Fire alarm upgrade or magnetic locksAlterations (AL)Named by the City as examples
Retail space becoming a restaurantNon-Housing (NH)Change of use is never an AL permit
Warehouse addition or new buildingNon-Housing (NH)Site plan, grading and servicing drawings
Plumbing onlyPlumbing (PP)Own Plumbing Data Form

Markham's Building Counter will confirm the permit type if your case sits between two rows. If the project changes what the space is used for, read our guide to change of use construction before you sign a lease.

What does Markham ask for in a tenant fit-up application?

Markham's Guide to Building Permits lists the papers for an interior alteration. The City says an application missing any of them cannot be processed.

  • Forms: the Building and Land Use Declaration, the Applicable Law Checklist, Schedule 1 Designer Information for each qualified designer, the Commitment to General Review where required, and the Plumbing Data Form. A Permit Applicant Authorization is added when the owner is not the applicant, and a General Review Commitment Authorization when a tenant signs the commitment.
  • Documents: approvals required by applicable law, heat loss, heat gain and duct calculations, and mechanical equipment and design specifications.
  • Architectural drawings: a zoning summary on the site plan, an Ontario Building Code data matrix, a key plan showing where the unit sits in the building, existing and proposed floor plans, fire separations, door and room finish schedules and sections.
  • Other trades, where they apply: structural framing plans, plumbing and fire protection drawings, and electrical and fire alarm zoning drawings.

The Declaration of Use deserves attention. The City requires it for every non-residential application, completed by the owner or tenant, and it asks whether the use includes retail sales to the public, wholesale sales or outdoor storage. If retail sales are proposed, the retail area must be outlined on the floor plans with dimensions, so a vague answer here leads straight to a zoning question.

How do I apply, and what does Markham do with the application?

Markham's building permit process runs through ePLAN in five steps: plan the project, submit online, plan review, approval and permit issue, then inspections. The City counts your application date from the day staff approve the pre-screen, not the day you upload.

  1. Check zoning with the City's Zoning Search tool, and for a non-residential project consider asking for a Zoning Preliminary Review in ePLAN first.
  2. Create or sign in to an ePLAN account, request a new application and pay the non-refundable pre-application fee. Drawings cannot be uploaded until it is paid.
  3. Upload drawings that meet the ePLAN submission standards. Staff run a pre-screen, and that approval date becomes your application date.
  4. Answer review comments electronically. Resubmissions and mark-ups all happen in ePLAN, with email notices.
  5. Download the approved plans, then print the permit card, the permit placard and one set of plans for the site.

The City warns that an application inactive for six months or more may be treated as abandoned. It names the common delays as incomplete drawings, zoning errors and missing applicable law approvals, so confirm early whether a conservation authority or City planning approval applies.

How long does Markham take to review a commercial permit?

Markham's first-review target for a non-housing interior alteration is 10 business days, and for a large building it is 20 business days for a complete application. The chart shows every non-housing target the City publishes, set against the longer target it gives an incomplete application.

Paired bar chart of Markham first review targets in business days for seven non-housing permit types, complete against incomplete applications
First-review targets in business days for non-housing permits, as published on the City of Markham building permit process page, read November 19, 2026. Chart drawn by us from those figures.

Three readings are worth planning around. Interior alterations, signs and demolition share the shortest target in the table at 10 business days. A small building outside housing is 15 days when complete and 30 when not, so completeness doubles the wait. And the City's own page says it cannot process an incomplete application, so the incomplete column is best read as the cost of getting the first upload wrong. The page states no timeline for occupancy approval, so ask the inspector rather than assume one.

What is different about a change of use in Markham?

A change of use in Markham is a Non-Housing permit, and zoning decides whether the use is allowed at all. A tenant who signs a lease before that check can pay for design and still be unable to open, because the zoning by-law, not the Building Code, permits the use.

The Declaration of Use is where Markham first sees the change, so describe the use, the customers it serves and any hazardous materials plainly. For food users, see our guide to restaurant construction, and for medical users our medical clinic construction page, because their equipment drives the mechanical and fire drawings the City reviews.

Which City office do you call in Markham, and for what?

Markham splits a commercial opening across four offices, and calling the wrong one costs days. This is the list to keep beside your drawings.

City of Markham contacts for commercial permit work. Source: City of Markham building permit, licensing and development charge pages, read November 19, 2026.
QuestionWho to contactHow
Permit status, forms, permit typeBuilding Standards Department[email protected], or the Building Counter
Book an inspectionBuilding StandardsePLAN portal, "Request a Building Inspection"
Development chargesDevelopment FinanceCity Development Finance staff, through the City's contact page
Business licenceBusiness Licensing[email protected]
Food or personal service health reportYork Region Public Health[email protected]

Building Standards is at 101 Town Centre Boulevard, open 8:30 am to 4:30 pm, Monday to Friday. Inspections are booked in the portal only, because the City says its inspection request phone line ended on January 1, 2021.

What inspections and papers come after the permit?

Markham requires inspections on every commercial, industrial and institutional project, on commercial and industrial tenant projects, and on any change of use. It adds life safety systems, commercial kitchen exhaust and fire suppression, spray booth exhaust and dust collection systems to the list. The inspection confirmation is emailed to the owner named on the permit.

Consultants who signed a general review commitment send their review reports and certificates, such as fire stopping, emergency power and magnetic lock certificates, as the work reaches each stage. Ask your designer when each one will arrive, because an open certificate is the most avoidable reason a file stays open.

When do development charges and a business licence come into it?

Markham's development charges page says all charges must be paid before a building permit is issued. Charges can apply to a new building, to an addition or alteration that increases floor area or the number of units, and to a redevelopment that changes the use. Non-residential charges combine gross floor area with site area, and the City indexes its rates on January 1 and July 1, so a permit paid in June and one paid in July may not use the same rate.

The business licence is a separate application. Markham's business licence page lists stationary businesses that need one under By-law 2018-90, including food premises, personal service shops, places of amusement and public halls. It asks for a zoning search letter for many types, a building permit number if the space was or will be renovated, and a York Region health inspection report for food and personal service uses. It also says partial applications are not reviewed and outstanding Building Code or Fire Code orders can delay a licence.

A checklist to have ready before you call

  • The unit address, landlord consent and the landlord's contractor rules.
  • A zoning answer, from the Zoning Search tool or a Zoning Preliminary Review, that your use is permitted.
  • A completed Declaration of Use with the retail, wholesale and outdoor storage questions answered.
  • Designers lined up for architectural, mechanical and electrical drawings, each with a Schedule 1.
  • An ePLAN account and a plan to meet the City's submission standards on the first upload.
  • Your licence type, and the health inspection step if you serve food or provide personal services.

For another city's steps beside these, read our Brampton building permit guide or our analysis of commercial permits in Mississauga. For the wider picture, ICI construction explained shows how the Building Code classifies these buildings.

How should the steps be ordered so a schedule holds?

Work backwards from the opening date. Zoning answer first, designers second, a complete ePLAN submission third, development charges and permit fourth, build and inspections fifth, licence and occupancy last. A gap in any earlier step moves everything after it, and Markham's 10 and 20 day targets only apply from a complete first submission.

Our office renovation, retail renovation and industrial building renovation projects follow that order.

When your papers are ready, send us the unit address, your use and your target opening date through our contact page for a written quote, and we will plan the build around the permit. You can also start from our tenant improvements page.

Frequently asked questions

Do I need a Markham building permit to renovate a commercial unit?

Yes, for most interior work. The City of Markham says permits are required for most new construction, additions, demolition and alterations, including interior work, and sign permits are required too. Confirm your exact case with the Building Standards Department before you start.

Is a change of use an alterations permit or a non-housing permit in Markham?

A change of use falls under the Non-Housing permit, not the Alterations permit. Markham gives changing a retail space to a restaurant as an example. A same-use tenant fit-up, fire alarm upgrade or magnetic lock installation is an Alterations permit.

How long does Markham take to review a commercial interior alteration?

Markham's first-review target for a non-housing interior alteration is 10 business days. The City measures it from payment of the pre-application fee for a complete application, and it says incomplete applications cannot be processed, so a complete first submission is what protects the date.

Can I apply for a Markham building permit on paper?

No. The City says paper applications are no longer accepted. You create or sign in to an ePLAN customer account, request a new application, pay the pre-application fee and upload drawings that meet the ePLAN submission standards.

Do I need a business licence as well as a building permit in Markham?

Only some businesses do. Markham licences stationary businesses such as food premises and personal service shops under By-law 2018-90, and its licensing page asks for a building permit number if the space was or will be renovated. It is a separate application from the permit.

When are development charges paid on a Markham commercial project?

The City says all development charges must be paid before a building permit is issued. They can apply to a new building, to an addition or alteration that increases floor area or the number of units, and to a redevelopment that changes the use.

Get a quote for your project

Tell us about the site, the scope, and your timeline. We review it and reply with the next step.

Free, no-obligation quote & on-site assessment

or
Call (416) 764-5999

← All guides

Companies We've Worked With

Trusted by Leading Organizations

Ardenvale Construction delivers industrial, commercial, and institutional construction for developers, contractors, institutions, municipalities, and property groups across Ontario.

Popeyes logo Popeyes
Tim Hortons logo Tim Hortons
Subway logo Subway
University of Toronto logo University of Toronto
Madison Group logo Madison Group
RioCan logo RioCan
Women's College Hospital logo Women's College Hospital
Starbucks logo Starbucks
Mazda logo Mazda
TD Bank logo TD Bank
City of Toronto logo City of Toronto
Brookfield Properties logo Brookfield Properties
Scotiabank logo Scotiabank
KPMG logo KPMG
Deloitte logo Deloitte
Wells Fargo logo Wells Fargo
Bell logo Bell
Popeyes logo Popeyes
Tim Hortons logo Tim Hortons
Subway logo Subway
University of Toronto logo University of Toronto
Madison Group logo Madison Group
RioCan logo RioCan
Women's College Hospital logo Women's College Hospital
Starbucks logo Starbucks
Mazda logo Mazda
TD Bank logo TD Bank
City of Toronto logo City of Toronto
Brookfield Properties logo Brookfield Properties
Scotiabank logo Scotiabank
KPMG logo KPMG
Deloitte logo Deloitte
Wells Fargo logo Wells Fargo
Bell logo Bell
Call now (416) 764-5999 Get a Quote